Results of the Open Meeting with LCC regarding the strengthening and potential closure of Skirden Bridge.

LCC answers in blue:

Why does the bridge need strengthening?
- Is the strengthening needed to meet an EU directive? Yes.
- Will all the bridges into and out of the village be strengthened? Yes How many? Perhaps one more in the local area - investigations are continuing.
- Who will fund the work? LCC
- Why not weight restrictions? - many already exist. - Impractical - It would prevent the movement of farm vehicles, fire engines etc.
- How many 44 tonnes vehicles have used the bridge in the last year/5 years? Not known
- How often will the bridge be subject to all 44 tonnes? Are axle weights not more important? No knowledge
- The assessment of LCC is that the bridge cannot accommodate 44 tonne vehcles. Has a risk assessment been completed. Yes, If so can we have a copy? Not offered by LCC
- What is the calculated maximum weight the current bridge structure can accommodate? 25 Tons No basis for this calculation was provided

If LCC insist that the bridge can be strengthened:

- Will the villagers have a temporary bridge for the duration of the work? No
- How long will the work take? One week setting up (lights) 4 weeks closed 1 week close (lights) - This is an estimate - it could be longer
- Can flood relief pipes be built into the structure, as discussed previously? No

If there is to be no temporary bridge:

- How long will the work take?
- What arrangements will be made for pedestrians? There will be pedestrian access over river at all times.
- What arrangements will be made for people who wish to park on the Copy Nook side of the bridge? LCC are meeting local landowner to investigate secure parking on the football field.
- Can the bridge be open to traffic early morning/late evening? No
- What arrangements will be made with regard to school buses and service buses? Planned for School holidays. LCC will liaise with schools.
- Will residents be compensated for any additional transport costs caused by the closure? People can write in and claim costs, such claims will be handled by LCC legal department
- Will local businesses be compensated for loss of earnings? People can write in and claim costs, such claims will be handled by LCC legal department

 

Start day - immediately local schools finish around 22nd July.